Hey, Daniel here. Every time I ask “how much to build a house?”, I get a different answer.
Short answer: 20k is a myth (unless you want bare concrete). 35k is realistic for “nice but simple”. 50k+ is where it starts looking like Pinterest.
Contractors quote low to get the job. “Sir, 25k per sqm only!” Then halfway through:
Suddenly your 25k house is 40k.
(don’t quote me on this, prices change every week seriously)
Structural (30-40%)
Finishes (30-40%)
MEP (Mechanical, Electrical, Plumbing) (10-15%)
The “Project Management” Fee (10-20%)
Don’t accept “global estimate”. Ask for the BOM. Line by line. “100 bags cement @ 230 pesos.” “500 hollow blocks @ 18 pesos.”
If they won’t give you a BOM? Run. They’re hiding something.
You can save like 20-30%. BUT. Do you know how to check rebar spacing? Do you know if the mix is wet enough? Do you have time to chase suppliers when the truck is late?
My friend tried this. Saved 500k. Aged 10 years in 6 months. Worth it? idk.
Budget what you think it costs. Add 20%. Then add another 10% for “oops”.
And whatever you do… never pay full upfront. Ever.